Construction Management and Supervision of Srinakharin – Romklao Road Section 4 Project
- Hits: 1719
Location :
Sapansoong, Bangkok Metropolitan Province
Client :
Department of Public Work, Bangkok Metropolitan Administration
Project Description :
Construction of 8 lane reinforced concrete road and associated works from Klong Wangmai to Highway No.9.
Type of Services :
Construction Management and Supervision
Scope of Works :
Construction management and supervision of 8 lane reinforced concrete road with sidewalks, roadway bridges, pedestrians crossing, drainage system, road lighting, traffic sign and associated works.
Project Costs :
584.40 Million baht
Consultant Fee :
14.97 Million baht
Project Period :
September 2015 – August 2017
Project Components :
- Main road : 2 ways 8 lanes reinforced concrete road distance is about 2,000 m.
- Frontage road : 2 ways 2 lanes reinforced concrete road distance is about 825 m.
- Ramp : No.1, 2, 5
- Roadway bridge (main road and frontage road) : Klong Tabchang Lang and Klong Luang.
- Pedestrian crossing : 2 nos.
- Drainage system : reinforced concrete pipe dia. 1000 mm.
- Retaining wall : Along right of way about 2-1400 m length.
- Road Lighting
- Traffic sign.